Do you have questions for our Environmental team? Click below to email them.
environmental.ccr@libertyutilities.com
Or
Liberty closed the Asbury coal plant on March 1, 2020. An impoundment is located at the former Asbury site for coal combustion residuals (CCR). Residual fly ash, bottom ash, and other related wastes were placed in the impoundment area until April 1, 2021, as part of the decommissioning activities. On April 1, 2021, a Notification of Intent to Close CCR Surface Impoundment was posted to the facility’s website and the State Director (MDNR) was notified. Dewatering of the impoundment occurred during the first part of 2022. CCR grading, excavation and relocation activities began in June of 2022. Closure of the CCR impoundment was completed on January 23, 2023, and the power plant was imploded that June. All remaining material was removed and the site was reclaimed by June 2024. As required by the Environmental Protection Agency's CCR Rule, this page provides information related to compliance, inspections and actions regarding the impoundment.
2015 Asbury CCR Fugitive Dust Control Plan
2016 Asbury Annual CCR Inspection
2016 Asbury CCR - History of Construction
2016 Asbury CCR - Initial Hazard Potential Classification
2016 Asbury CCR - Initial Inflow Design Flood Control Plan
2016 Asbury CCR - Initial Safety Factor Assessment
2016 Asbury CCR - Initial Structural Stability Assessment
2016 Asbury CCR - Liner Design Criteria
2016 Asbury CCR Impoundment Closure
2016 Asbury CCR Impoundment Post Closure
2017 - Asbury - CCR Emergency Action Plan
2017 - Groundwater Certification CCR
2017 Asbury Annual CCR Inspection
2017 Groundwater Monitoring Annual Report CCR
2018 – CCR Annual Fugitive Dust Report
2018 Asbury Annual CCR Inspection
2018 Asbury CCR Impoundment Closure
2018 Asbury CCR Location Restriction
2018 Groundwater Monitoring Annual Report CCR
2019 Annual CCR Emergency Action Plan Review
2019 Annual Report - Asbury CCR Impoundment GW Sampling
2019 Asbury Annual CCR Inspection
2019 CCR Annual Fugitive Dust Report
2020 Annual Asbury CCR Inspection Report
2020 Annual Asbury CCR Impoundment Groundwater Report
2021 Annual Asbury CCR Inspection Report
2021 Annual Asbury CCR Location Restriction Report
2021 Updated Asbury CCR Impoundment Closure Report
2021 Notification of Intent to Close
2021 Periodic Structural Stability Assessment
2021 Periodic Safety Factor Assessment
2021 Periodic Inflow Design Flood Control System Plan
2021 Periodic Hazard Potential Classification
2021 Annual Asbury CCR Impoundment Groundwater Report
2021 Annual Fugitive Dust Report
2022 Annual Asbury CCR Inspection Report
2022 Asbury CCR Impoundment Closure Plan
2022 Asbury CCR Impoundment GW Monitoring Report
2022 Asbury CCR Impoundment GW Sampling Report
2022 Fugitive Dust Plan Annual Report
2022 Asbury CCR Impoundment GW Sampling Report
2022 Fugitive Dust Plan Annual Report
2023 EPA Notification of Closure
2023 Annual Asbury CCR Inspection Report
2023 Asbury CCR Impoundment Closure
2023 Asbury CCR Impoundment Post-Closure Plan
2023 Asbury CCR Impoundment Closure-Final
2023 Asbury CCR Impoundment Post Closure-Final
2023 Asbury History of Construction
2023 Asbury Emergency Action Plan Update
2023 Asbury Periodic Hazard Potential Classification
2023 Fugitive Dust Plan Annual Report
2023 Asbury CCR Impoundment GW Sampling Report
2024 Periodic Safety Factor Assessment
2024 Periodic Inflow Design Flood Control
2024 Periodic Structural Stability Assessment
2024 Fugitive Dust Plan Annual Report
2024 Annual Groundwater Sampling Report
Users of Internet Explorer may experience issues downloading PDFs. Please press the F5 key during download to resolve this issue.
Liberty ceased burning coal on Sep 18, 2012, at the Riverton Power Station facility. On Aug 23, 2013, closure construction activities for the Riverton Industrial Landfill began under Kansas Department of Health & Environment (KDHE) Permit 784. Construction was completed May 22, 2014. KDHE approved closure on June 30, 2024, and entered into Post-Closure Care. On July 31, 2018, the demolition of the remaining coal-fired boilers of the Riverton Power Station was completed and the site improvements were completed to reclaim the area. CCR is no longer produced at this site. As required by the Environmental Protection Agency's CCR Rule, this page provided information related to compliance, inspections and actions regarding the CCR Management Unit (CCRMU).
Do you have questions for our Environmental team? Click below to email them.
environmental.ccr@libertyutilities.com
Or